Mumbai Metro Line-3 is 81.3% complete, says MMRCL

Patna metro project

Mumbai Metro Line 3, also known as the Aqua Line, is 81.3% complete. This is Mumbai’s first underground metro and will connect South Mumbai to the Western suburbs.

The 33.5 km line has 28 stations and is divided into two phases. The first phase is from Aarey to BKC and the second phase is from BKC to Cuffe Parade.

According to data tweeted by Mumbai Metro 3, as on April 30, 2023, the Aqua Line’s overall civil work completed is 92.7%, the overall systems works completed is 50.5%, overall station construction is 89.7% completed, depot works is 62% completed,  mainline track works completed is 60.6% and tunneling completed is 100%.

 

Phase 1 completion status

Aarey to BKC has achieved 87% completion.

Works Status
Overall systems works 64.7% completed
OCS works 57.9% completed
Mainline track works 85.2% completed
Station and tunnel works 97.7% completed
Overall station construction 92.9% completed

 

Phase 2 completion status

BKC to Cuffe Parade has achieved 76.8% completion.

Works Status
Overall systems works 42.2% completed
OCS works 46.3% completed
Mainline track works 46.5% completed
Station and tunnel works 95.2% completed
Overall station construction 88.1% completed

 

 

 