November 22, 2023: The real estate regulatory authority of Maharashtra (MahaRERA) on November 20, 2023 suspended registration of over 248 realty projects. This also includes three projects that were to be developed by the Maharashtra Housing and Area Development Authority (MHADA).

The regulator has taken this action owing to these projects failing to update their quarterly progress report (QPR) by July 20, 2023. It is mandatory to upload the QPR on the MahaRERA website so that homebuyers are abreast of the construction status.

Of the 248 projects, 99 cancelled projects are in the Mumbai Metropolitan Region (MMR) and Konkan, 69 projects are in western Maharashtra, 28 in north Maharashtra and 40 in Vidarbha.

On the same lines, the MahaRERA has already issued notices to around 224 projects of the total 443 projects that were registered in March 2023. These projects were directed to update the QPR by October 20, 2023. Similar suspension action will be taken against projects that don’t comply with the regulation.

 

Got any questions or point of view on our article? We would love to hear from you. Write to our Editor-in-Chief Jhumur Ghosh at jhumur.ghosh1@housing.com

 

Was this article useful?
  • ? (1)
  • ? (0)
  • ? (0)

Recent Podcasts

  • Keeping it Real: Housing.com podcast Episode 92Keeping it Real: Housing.com podcast Episode 92
  • Keeping it Real: Housing.com podcast Episode 91Keeping it Real: Housing.com podcast Episode 91
  • Keeping it Real: Housing.com podcast Episode 90Keeping it Real: Housing.com podcast Episode 90
  • Keeping it Real: Housing.com podcast Episode 89Keeping it Real: Housing.com podcast Episode 89
  • Keeping it Real: Housing.com podcast Episode 88Keeping it Real: Housing.com podcast Episode 88
  • Keeping it Real: Housing.com podcast Episode 87Keeping it Real: Housing.com podcast Episode 87