Work on the 33.5km Mumbai Metro Line-3, also known as the Aqua Line, is 79.8% complete, says Mumbai Metro Rail Corporation Ltd (MMRCL) in a tweet. There are 28 stations in this first underground Mumbai Metro rail. Divided into phases, phase-1 runs from Aarey to BKC while phase-2 operates between BKC to Cuffe Parade.
As of February 28, 2023, the Aqua Line’s overall civil works completed is 91.3%, the overall systems works completed is 47.5%, the track works complete is 55.6%, overall station construction is 88.7% and tunnelling completed is 100%.
Have a look at the overall project progress of #MetroLine3 as of 28th February 2023.#𝐋𝐢𝐧𝐞𝟑𝐈𝐧𝟐𝟎𝟐𝟑 #𝐀𝐪𝐮𝐚𝐋𝐢𝐧𝐞 pic.twitter.com/u8dImYU3Z6
— MumbaiMetro3 (@MumbaiMetro3) March 11, 2023
Source: MMRCL twitter
Phase-wise project completion breakup
According to a tweet by Ashwini Bhide, MD Mumbai Metro Corporation, Mumbai Metro 3 as on February 28,2023 has achieved 85.2% progress in Phase 1 (from Aarey to BKC) and 76% progress in phase 2 (BKC to Cuffe Parade).
Got any questions or point of view on our article? We would love to hear from you.
Write to our Editor-in-Chief Jhumur Ghosh at [email protected] |
With 16+ years of experience in various sectors, of which more than ten years in real estate, Anuradha Ramamirtham excels in tracking property trends and simplifying housing-related topics such as Rera, housing lottery, etc. Her diverse background includes roles at Times Property, Tech Target India, Indiantelevision.com and ITNation. Anuradha holds a PG Diploma degree in Journalism from KC College and has done BSc (IT) from SIES. In her leisure time, she enjoys singing and travelling.
Email: [email protected]