Work on Mumbai Metro Line-3, also known as the Aqua Line, is 79% complete, says the Mumbai Metro Rail Corporation Ltd (MMRCL). As of January 31, 2023, the Aqua Line’s overall civil works completed is 90.6%, the overall systems works completed is 46.1%, the track works complete is 53.8%, overall station construction is 88.3% and tunneling completed is 100%.
The 33.5-km Aqua Line with 28 stations is the first underground metro in Mumbai. Phase-1 runs from Aarey to BKC while Phase-2 will operate from BKC to Cuffe Parade.
Media reports mention that Phase-1 of the Mumbai Metro from Aarey to BKC will be operational from December 2023.
Ashwini Bhide, MD, Mumbai Metro corporation tweeted the status of Mumbai Metro 3.
Project progress status of @MumbaiMetro3 project by end of January 2023. https://t.co/jRvPC32fL7
— Ashwini Bhide (@AshwiniBhide) February 6, 2023
Phase-wise project completion breakup
According to MMRCL data, Phase -1 of the Aqua Line is from Aarey to BKC and is 84% completed.
- Station and tunnel works: 97.1%
- Overall systems works: 59.1%
- Overall station construction: 91,3%
- Track works: 70.6%
- OCS works: 56.3%
Phase -2 of Aqua line is from BKC to Cuffe Parade and is 75.6% completed.
- Station and tunnel works: 94.5%
- Overall systems works: 39.6%
- Overall station construction: 86.3%
- Track works: 44.2%
- OCS works: 45.8%
With 16+ years of experience in various sectors, of which more than ten years in real estate, Anuradha Ramamirtham excels in tracking property trends and simplifying housing-related topics such as Rera, housing lottery, etc. Her diverse background includes roles at Times Property, Tech Target India, Indiantelevision.com and ITNation. Anuradha holds a PG Diploma degree in Journalism from KC College and has done BSc (IT) from SIES. In her leisure time, she enjoys singing and travelling.