Mumbai Metro Line-3 is 80.6% complete

The 33.5 km Aqua line or Mumbai Metro 3 with 28 stations is the first underground metro in Mumbai.

Work on the 33.5km Mumbai Metro Line-3, also known as the Aqua Line, is 80.6% complete, says Mumbai Metro 3 in a tweet. 

Aqua Line has 28 stations and is the first underground Mumbai Metro rail. Divided into phases, phase-1 runs from Aarey to BKC while phase-2 operates between BKC to Cuffe Parade. While Aarey to BKC has achieved 86.4% completion, BKC to Cuffe Parade is 76% complete.

Phase-1 of Aqua Metro is expected to be operational by December 2023.

As of March 31, 2023, the Aqua Line’s overall civil works completed is 92.2%, the overall systems works completed is 49%, overall station construction is 89.2% completed, depot works is 59.5% completed,  mainline track works completed is 58.5% and tunneling completed is 100%.

Phase-wise project completion breakup

Mumbai Metro 3 Phase-I completion status

Mumbai Metro 3

Source: Mumbai Metro 3 twitter

Mumbai Metro 3 Phase- II completion status

Mumbai Metro 3

Source: Mumbai Metro 3 twitter

Mumbai Metro 3

Source: Mumbai Metro 3 twitter

 

Got any questions or point of view on our article? We would love to hear from you.

Write to our Editor-in-Chief Jhumur Ghosh at jhumur.ghosh1@housing.com

 

Was this article useful?
  • 😃 (0)
  • 😐 (0)
  • 😔 (0)

Recent Podcasts

  • Keeping it Real: Housing.com podcast Episode 47Keeping it Real: Housing.com podcast Episode 47
  • Keeping it Real: Housing.com podcast Episode 46Keeping it Real: Housing.com podcast Episode 46
  • Keeping it Real: Housing.com podcast Episode 45Keeping it Real: Housing.com podcast Episode 45
  • Keeping it Real: Housing.com podcast Episode 44Keeping it Real: Housing.com podcast Episode 44
  • Keeping it Real: Housing.com podcast Episode 43Keeping it Real: Housing.com podcast Episode 43
  • Keeping it Real: Housing.com podcast Episode 42Keeping it Real: Housing.com podcast Episode 42